VBL, a part of RJ Corp Group and PepsiCo’s franchisee, manufactures, distributes, and sells a wide range of Carbonated Soft Drinks (CSD) and Non-Carbonated Beverages (NCB) including packaged drinking water. VBL is a diversified business conglomerate with interests in beverages, quick-service restaurants, ice-creams, and healthcare.
Brands of PepsiCo produced and sold by VBL apart from packaged drinking water under the brand Aquafina include;
VBL wanted to set up a green field project in the Congo for carbonated soft drinks. They wanted to tap into the African market with their carbonated beverages. To do so they required processing lines that could produce highly concentrated beverages to meet the rising demand for CSD beverages. Here, Neologic Engineers stepped in to provide state-of-the-art beverage processing equipment to meet their needs.
Neologic Engineers designed a beverage processing plant that was uniquely engineered to their requirements. The beverage processing equipment supplied by them consisted of:
While commissioning the plant at the Congo site, there were adverse health conditions. Localities were falling sick in huge amounts due to the widespread dengue. Despite the adversity, the Neologic Engineers project team completed and handed over the project on time. They ensured that all the staff members working on-site maintained hygienic conditions by conducting proper sanitization activities and regular employee health checks.
After handing over the project, a trial production was conducted. In this trial, VBL could successfully process their carbonated soft drinks with the desired results. The equipment supplied by Neologic Engineers proved to be of top-notch quality and delivered as promised.
“We have been working with Neologic Engineers for the past 10-12 years and they have understood our needs and requirements and provided us with meticulously designed process solutions each time. We acknowledge the sincere efforts, hard work, flawless site coordination, consistent progress on daily activities, and delivery of quality work done by the Installation team on site. The Neologic Engineers Project team has shown exceptional commitment towards every support needed by us throughout the project.”